Our Projects
- Commercial
- Education
- Healthcare
- Industrial
- Residential
- Conservation & Restoration
- Infrastructure
- Leisure & Hotels
- Public Buildings
- International
- ALAT Free Economic Zone
- Kabwe to Kapiri Mposhi & Chisamba Roads
- Medical Centre, Doha
- West Coast Sewerage, Mauritius
- Dr. Soliman Fakeeh Hospital
- Kamplala Industrial & Business Park
- ICT Park, Accra
- General Hospital, Jeddah Housing Complex
- Rayadah Housing Complex
- Trade Gateway Project
- Andalus Educational Complex
- Xtratherm Facility, Belgium
Feeling Social?
Kabwe to Kapiri Mposhi & Chisamba Roads
Project: | Kabwe to Kapiri Mposhi & Chisamba Roads, Zambia |
Completion Date: | 2004 |
Client: | The Government of the Republic of Zambia |
Project Value: | €11.8m |
Services Provided: | Civil and structural engineering, project management |
Project Size: | 82km Roadway |
Project Description
Garland was appointed in 2001 to act as supervisor’s representative on a contract for the reconstruction of the Kabwe-Kapiri Mposhi and Chisamba Roads. The contract consisted of the rehabilitation of a total of 82km of road together with miscellaneous associated works. The 62km long Kabwe-Kapiri Mposhi section comprised of the construction of a new pavement over a carriageway width of 6.90m with 1.90m wide hard shoulders each side. The pavement specification for the main carriageway is 50mm asphalt wearing course on a 150mm crushed stone base on 200mm sub-base over the existing road. The hard shoulders consist of a double surface dressing on 150mm crushed stone base on 350mm sub-base.
For the 20km long Chisamba section, the repairs comprised of the construction of a new pavement consisting of a double surface dressing on a 200mm cement stabilised base on 150mm sub-base on 300mm sub-grade. The carriageway is 6.10m wide with 1.95m wide hard shoulders on each side.
Our scope of works included:
- Review of contract documents
- Re-design of the horizontal and vertical alignments along much of the roads
- Contract supervision